Close Menu
BmoreNews.com
  • News
  • Politics
  • Business
  • Editorial/Op-Ed
  • The Glover Report
  • Black Wall Street
  • Video
  • More
    • BEOs
    • HBCU
    • Africa/Caribbean
Trending
In Maryland’s Statewide Elections, Character Matters More Than Campaign Slogans

In Maryland’s Statewide Elections, Character Matters More Than Campaign Slogans

Doni Glover Show LIVE, 2.5.26 @The Thurgood Marshall Amenity Center #bmorenews

Doni Glover Show LIVE, 2.5.26 @The Thurgood Marshall Amenity Center #bmorenews

Congressman Mfume Salutes Benedetto: Arnold Williams From ’79 to ’26: A Special Reunion

Congressman Mfume Salutes Benedetto: Arnold Williams From ’79 to ’26: A Special Reunion

Facebook X (Twitter) Instagram
  • About
  • Advertise
  • Contact
Facebook X (Twitter) YouTube
BmoreNews.com
  • News
  • Politics
  • Business
  • Editorial/Op-Ed
  • The Glover Report
  • Black Wall Street
  • Video
  • More
    • BEOs
    • HBCU
    • Africa/Caribbean
Newsletter
BmoreNews.com
  • News
  • Politics
  • Business
  • Editorial/Op-Ed
  • The Glover Report
  • Black Wall Street
  • Video
Home » Frederick Douglass Tunnel Program – Construction Activities
News

Frederick Douglass Tunnel Program – Construction Activities

Staff ReporterBy Staff ReporterSeptember 22, 2024203 ViewsNo Comments2 Mins Read
Share Facebook Twitter Pinterest Telegram LinkedIn Tumblr Email Copy Link
Follow Us
Google News Flipboard
Frederick Douglass Tunnel Program – Construction Activities
Frederick Douglass Tunnel Program

Upcoming Activities

Demolition

  • The Medical Facility structure at 920 W. North Avenue is scheduled to be demolished. In preparation for demolition, you may observe: the placement of dumpsters to support site preparation and tree removal. All activities will take place on the property within the fenced area with the exception of the possible removal of a curbside tree.
  • Site preparation is scheduled to begin next week, with completion of debris and tree removal followed by interior clean-out through October 7, 2024. Typical work hours are 8AM to 5PM Monday through Saturday, with the possibility of Sunday work if needed.
  • This work is not anticipated to impact the surrounding sidewalks or traffic patterns
  • There may be an increase in truck traffic and dust during the demolition. We plan to mitigate the increased dust with the use of watering hoses when necessary.

Demolition

  • Demolition at 1034 N. Payson Street has been completed. Crews will be completing site clean-up and the installation of the permanent fence.

Tree Removal

  • Crews will be onsite at 2126 Edmondson Avenue to install fencing and remove some trees through October 7,2024 weather permitting.

Locating Utilities

  • Next week crews will begin locating utilities on the following roadways:
  • Lanvale Street, Pulaski Street, Brice Street
  • This work is scheduled to start at 7AM and end at 5PM
  • Expect to see crew members inspecting manholes and inlets in the roadway
  • There will be no traffic modifications or sidewalk closures

For more information about these projects, please visit FDTunnel.com, call 443-423-1115, or email fdtunnel@amtrak.com

Construction activities are subject to change. Modifications to the schedule may become necessary due to weather delays or other unforeseen conditions.

Frederick Douglass Tunnel Program - Construction Activities
Share. Facebook Twitter Pinterest LinkedIn Tumblr Email Copy Link
Previous ArticleTaco Tuesday Pop Up & Book Signing: BOOK SIGNING ALERT!
Next Article The Glover Report: Dear Republican Party …

Keep Reading

Faith-Based Community Breakfast at Morgan State, March 19th
February 28, 2026

Faith-Based Community Breakfast at Morgan State, March 19th

By Doni Glover
Tune in to BMORENews: Unapologetically Baltimore
February 28, 2026

Tune in to BMORENews: Unapologetically Baltimore

By Doni Glover
February 28, 2026

BMORENews: Unapologetically Baltimore

By Doni Glover
Black History Month 2026 | Baltimore & Beyond
February 22, 2026

Black History Month 2026 | Baltimore & Beyond

By Doni Glover
Two Black Press Institutions Close Within Days — What It Means for Community Journalism
February 14, 2026

Two Black Press Institutions Close Within Days — What It Means for Community Journalism

By Doni Glover
Passing of Mrs. Margaret L. Jones
February 12, 2026

Passing of Mrs. Margaret L. Jones

By Julian Jones
Add A Comment
Leave A Reply Cancel Reply

Latest News
Doni Glover Show LIVE, 2.5.26 @The Thurgood Marshall Amenity Center #bmorenews

Doni Glover Show LIVE, 2.5.26 @The Thurgood Marshall Amenity Center #bmorenews

Congressman Mfume Salutes Benedetto: Arnold Williams From ’79 to ’26: A Special Reunion

Congressman Mfume Salutes Benedetto: Arnold Williams From ’79 to ’26: A Special Reunion

Bishop John Bryant Speaks: Baltimore’s Superstar – Discipline, Dreams & Fashion Icon!

Bishop John Bryant Speaks: Baltimore’s Superstar – Discipline, Dreams & Fashion Icon!

Alexis Solis for Congress (5th): Mental Health Advocate Becomes Political Fighter For Community

Alexis Solis for Congress (5th): Mental Health Advocate Becomes Political Fighter For Community

Trending News
Par’ris Rose Business Networking Event in Baltimore

Par’ris Rose Business Networking Event in Baltimore

March 1, 2026
Kevin Scott of Benedetto Haberdashery Speaks on Black Wall Street Event

Kevin Scott of Benedetto Haberdashery Speaks on Black Wall Street Event

February 28, 2026
Algia Ford, Clothier, Recognized by BMORENews at Benedetto

Algia Ford, Clothier, Recognized by BMORENews at Benedetto

February 28, 2026

Subscribe to News

Get the latest Baltimore news and updates directly to your inbox.

Facebook X (Twitter) YouTube
2026 © BmoreNews.com. All Rights Reserved.
  • Doni Glover
  • Privacy Policy
  • Terms
  • Contact

Type above and press Enter to search. Press Esc to cancel.